Monthly Status Report – September 2023
The User & System Readiness phase continues with a focus on testing. In mid-September, the project team began Integrated Testing Round 2, which validates the workflows Woman’s end users will utilize. The project team also kicked off Parallel Revenue Cycle Testing, which focuses on mirroring real-life claims. Go-Live Readiness Assessments (GLRA) provide identification and mitigation plans for project risks and are scheduled at 30-day increments prior to Go-Live. Woman’s Project Champions and the IT team completed the GLRA process for the 120 Day event and workgroup leaders will participate in the upcoming 90-Day event.